Guide to Building a Verandah in Victoria

April 8, 2026

Adding a verandah to your home is one of the most rewarding ways to extend your living space and enjoy the outdoors year-round. But before you start picking out roofing materials or choosing a builder, there are important planning, permit, and compliance steps you need to understand.

This guide walks you through everything Victorian homeowners need to know about building a verandah — from what it actually is, to whether you need a permit, and how to make sure your project is compliant from day one.

What Is a Verandah?

A verandah is a roofed, open-sided structure attached to the exterior of a house. It typically extends along one or more walls and provides a covered outdoor area for relaxing, entertaining, or simply enjoying the view.


Verandahs are sometimes confused with similar structures, but there are important differences. A pergola has an open roof framework rather than full roofing, offering partial shade rather than weather protection. A deck is an unroofed raised platform, while a patio is usually an unroofed paved area at ground level. A verandah combines the attachment and roofing elements that set it apart — and those same features are what bring it into the scope of building regulations.


Under the Victorian Building Regulations 2018, a verandah attached to a Class 1a dwelling is typically classified as part of that dwelling or as a Class 10a structure (a non-habitable building), depending on its design and use. This classification matters because it determines which regulations apply and whether a building permit is needed.

Benefits of Building a Verandah

There are plenty of good reasons Victorian homeowners choose to add a verandah to their property. A well-designed verandah extends your usable outdoor living space, giving you a sheltered area for meals, gatherings, or quiet mornings with a coffee — regardless of the weather.

Verandahs provide valuable shade during Melbourne's summer months and protection from rain, meaning your outdoor furniture and entertaining areas stay usable for more of the year. They also add aesthetic appeal and street presence to a home, which can contribute to property value.

From a practical standpoint, a verandah can reduce heat gain through windows and external walls, contributing to energy efficiency. It can also serve as a functional transition space between indoor and outdoor areas, making the home feel more spacious and connected to the garden.

Do You Need a Permit to Build a Verandah in Victoria?

This is the question most homeowners ask first — and the answer, in most cases, is yes.

Under the Building Act 1993 and the Building Regulations 2018, most verandah projects require a building permit. This is because a verandah typically involves a roofed structure attached to the house, with footings, structural connections, and roofing that all need to comply with the National Construction Code (NCC) and Victorian siting regulations.


A building permit ensures the structure is designed and built to meet safety and performance standards. It must be issued by a Relevant Building Surveyor (RBS) — either a private building surveyor or the municipal building surveyor — before construction begins.

Are any verandahs exempt from a building permit?

There are limited exemptions under Schedule 3 of the Building Regulations 2018, but they apply to very specific circumstances. For example, a freestanding Class 10a building (such as a garden shed) may be exempt if it has a floor area not exceeding 10 m², is no more than 3 metres in height (or 2.4 metres if within 1 metre of a boundary), and is not constructed of masonry (Schedule 3, Item 1). A pergola may be exempt if it has a floor area not exceeding 20 m² and meets specific siting requirements (Schedule 3, Item 16).

However, these exemptions generally do not apply to a typical verandah that is attached to the house and includes a roof. The safest approach is always to check with a building permit professional before assuming your project is exempt. 

What about planning approval?

In addition to a building permit, some verandah projects may also require planning approval from the local council. This is particularly likely if your property is affected by zoning overlays, heritage overlays, neighbourhood character overlays, or vegetation protection controls.

It's important to understand that a building permit cannot be issued where a planning permit is required but has not yet been obtained. Checking with your council early in the process can avoid costly delays

Verandah Building Regulations in Victoria

Once you've established that a building permit is needed, your verandah will need to comply with a range of requirements under the Building Regulations 2018 and the NCC Volume Two. While your building surveyor will assess compliance in detail, here's a high-level overview of the key areas:


Structural requirements — Your verandah must be structurally sound. Footings, posts, beams, and roof connections all need to be designed to handle wind loads, dead loads, and live loads applicable to your site. Engineering details may be required, particularly for larger or more complex designs.

Boundary setbacks — Under Regulation 79, buildings must be set back from side and rear boundaries by specified distances depending on building height. At 3.6 metres or less, the minimum setback is 1 metre. Porches and verandas may encroach up to 500 mm into the required setback under Regulation 79(4)(a), but this still needs to be assessed against the overall design. If the verandah does not comply with the required setbacks, a report and consent from the relevant council will be needed under Regulation 79(6).

Overshadowing — Under Regulation 83, the verandah must not unreasonably overshadow the recreational private open space (RPOS) of an adjoining property. The assessment is based on shadow cast between 9 am and 3 pm on 22 September (the equinox), and the adjoining property's RPOS must retain at least 5 hours of sunlight over that period.


Overlooking — If the verandah includes a raised floor or deck above 800 mm, Regulation 84 may apply, requiring measures to limit views into a neighbouring property's habitable room windows or private open space.

Stormwater drainage — Under Regulation 133, the design of the stormwater drainage system must be approved by the building surveyor, and a report from the relevant council indicating the point of discharge must be obtained. Adding a roofed verandah increases the impervious area of your site, so stormwater management needs to be properly addressed.

Site coverage and permeability — Under Regulations 76 and 77, the verandah roof will contribute to total site coverage and reduce the permeable area of your allotment. These need to stay within the prescribed limits for your zone.

Daylight to habitable room windows — Under Regulation 85, the verandah must not block adequate daylight to the habitable room windows of the proposed building. A window may face a verandah provided the verandah is sufficiently open — generally open for at least one-third of its perimeter.

Steps to Getting a Verandah Building Permit

The process for obtaining a building permit for your verandah generally follows these steps:

1. Initial assessment — Determine whether a building permit is required and whether planning approval is also needed. Check for any overlays, easements, or other site constraints that may affect the project.

2. Prepare documentation — You'll typically need architectural drawings (plans, elevations, and sections), a site plan showing the verandah's position relative to boundaries and existing structures, and engineering details if required. Documentation must be sufficient for the building surveyor to assess compliance with the Building Regulations 2018 and the NCC.

3. Obtain required reports — Depending on the project, you may need a council report for stormwater point of discharge (Regulation 133), and possibly a report and consent for any siting variations (e.g., reduced setbacks under Regulation 79(6) or boundary wall provisions under Regulation 80(6)).

4. Lodge the building permit application — Submit your application with all supporting documentation to your chosen Relevant Building Surveyor. The RBS will review the plans, assess compliance, and issue the permit once satisfied.

5. Construction and inspections — Once the permit is issued, construction can begin. Under Regulation 167, mandatory inspection stages typically include before placing a footing, before pouring in-situ reinforced concrete (if applicable), completion of framework, and a final inspection on completion of all building work. The RBS may omit stages that are not relevant to the specific project under Regulation 170.

6. Final inspection and completion — After the final inspection, the RBS will issue either an occupancy permit or a certificate of final inspection, confirming the work has been completed in accordance with the building permit.

Common Mistakes Homeowners Make

Building a verandah might seem straightforward, but there are several common pitfalls that can lead to delays, additional costs, or compliance issues:


Building without a permit — This is the most serious mistake. Undertaking building work without a required permit is an offence under the Building Act 1993. It can result in enforcement action, building notices, and orders to modify or remove non-compliant work. Even if the structure is sound, retrospective permits can be difficult and expensive to obtain.

Assuming small verandahs don't need approval — Many homeowners believe that a small or simple verandah doesn't require a permit. In most cases, if the verandah is attached to the house and has a roof, a permit is required regardless of size. The Schedule 3 exemptions are narrow and apply to specific structure types — not to attached verandahs generally.

Not checking planning overlays — A property may be subject to heritage, neighbourhood character, or other overlays that require planning approval in addition to a building permit. Failing to check can mean the building permit cannot be issued until planning approval is obtained, causing significant delays.

Incomplete documentation — Submitting plans that lack sufficient detail — missing site dimensions, unclear structural details, or no stormwater information — will result in requests for further information and slow down the permit process.

Starting construction before approvals are issued — Even if you've lodged an application, building work cannot lawfully commence until the building permit has been issued. Starting early risks non-compliance and potential enforcement action.

How Code HQ Can Help

Navigating the building permit process doesn't have to be complicated. Code HQ specialises in building permits and compliance for Victorian homeowners, and can guide you through every step of the process.

Code HQ can help by assessing whether your verandah project requires a building permit and identifying any planning considerations early. They prepare and manage building permit applications, ensuring all documentation meets the requirements of the Building Regulations 2018 and the NCC. Code HQ liaises with building surveyors and councils on your behalf, handles any report and consent requirements, and helps you avoid the delays and compliance issues that trip up homeowners who try to manage the process themselves.

Whether you're adding a simple covered outdoor area or a more substantial verandah extension, having an expert manage the permit process means you can focus on enjoying the result — with confidence that it's been done properly.

Conclusion

A verandah is a fantastic addition to any Victorian home, extending your living space and adding value to your property. But it's important to get the planning, permits, and compliance right from the start. Most verandah projects require a building permit, and many will also need to satisfy siting, stormwater, and potentially planning requirements.

Before you start your verandah project, get expert advice to make sure everything is in order. Code HQ can help you navigate the process and ensure your verandah is compliant from start to finish. Ready to get started? Contact Code HQ today for expert help with your verandah building permit. 

Frequently Asked Questions

Do I need a building permit for a verandah in Victoria?
In most cases, yes. A building permit is generally required if the verandah is attached to your home and includes a roof. The permit ensures the structure complies with the Building Regulations 2018 and meets structural and safety standards. A Relevant Building Surveyor must review and approve the application before construction can begin.

How much does a verandah building permit cost in Victoria?
The cost varies depending on the size and complexity of the structure, as well as the fees charged by the building surveyor. Permit costs typically include application fees, documentation preparation, and fees for mandatory inspections during and after construction. Contact Code HQ for an estimate based on your specific project.

Do verandahs need council approval in Victoria?
Some verandah projects require planning approval from the local council, particularly if the property is affected by zoning rules, heritage overlays, or other planning controls. In addition, most verandahs require a council report for stormwater point of discharge under Regulation 133, and a report and consent may be needed if the design does not comply with siting requirements such as boundary setbacks.

What size verandah can you build without a permit in Victoria?
The exemptions under Schedule 3 of the Building Regulations 2018 are limited and generally apply to specific freestanding structures — such as small sheds under 10 m² or pergolas under 20 m² — not to attached roofed verandahs. If the verandah is attached to your house and includes a roof, a building permit is almost certainly required regardless of size.

Can I add a verandah to an existing house?
Yes, verandahs are commonly added to existing homes. However, the addition will usually require a building permit to ensure it complies with structural requirements, siting regulations, and stormwater management provisions. Your building surveyor will assess the connection to the existing structure and any impact on neighbouring properties.

How long does it take to get a verandah permit in Victoria?
Timeframes vary depending on the complexity of the project and whether planning approval or report and consent from council is required. Once all documentation is submitted and complete, the permit assessment process typically takes a few days. Incomplete applications or the need for additional reports can extend this timeline.

What documents are needed for a verandah building permit?
You'll typically need architectural drawings (floor plan, elevations, and sections), a site plan showing the verandah's position relative to boundaries and existing buildings, and engineering details where structural certification is required. A council report for stormwater point of discharge is also needed. Your building surveyor may request additional information depending on the specific design and site conditions.